£19m budgeted. £216.5m lost.

Birmingham City Council replaced its SAP system with Oracle.

ERP LEADERS news desk · · First reported by The Register · Edition no. 1

The 2021 business case put it at £19 million plus £1 million contingency, live in April 2022.

It went live. The council's own forecast cost of the programme to 2027/28 is now £144.4 million. Investigators put the total money lost, overspend plus the savings that never arrived, at £216.5 million. The Register works that out at roughly £200 for every person living inside the council boundary.

Two lines in that record matter more than the headline number. Fraud detection audits were switched off for more than 18 months. And £2 billion of transactions landed in the wrong financial year, inside a system meant to steward £3 billion of taxpayer revenue.

Go-live day cost the council very little. The eighteen months afterwards did the damage, with the controls that would have caught it turned off to keep the system moving.

If your finance system lost its audit trail this quarter, how long before anyone noticed?

Sources

Spotted an error? Tell us. Every correction is logged on Standards.

Your reading room

Companies in this story

Our file on SAP

  1. 20 SeptFiled later

    SAP's chief executive said voice replaces much data entry in three years.

  2. 19 SeptFiled later

    KPMG cut jobs in its SAP and AI teams. Partners averaged £880,000.

  3. 17 SeptFiled later

    Broadcom raised VMware prices by 10x or more, European cloud providers say.

  4. 17 SeptFiled later

    Grocery Outlet's SAP launch cut gross margin by almost 2 points.

  5. 11 SeptFiled later

    Zeiss dropped the clean rebuild of its SAP after about €200 million.

All 18 SAP stories

For your next steering committee

Questions for your own programme. They are not findings about any company in this story.

  1. 1Ask for the approved budget and the current forecast on the same scope, side by side.
  2. 2Ask which costs sit outside the programme budget today: internal staff, data migration, parallel running.
  3. 3Ask who may approve the next increase, and at what amount the programme goes back to the board.

Issue 01 of the ERP LEADERS brief puts a timeline, the three-number review and six questions on one page. Read issue 01

Founding reader view is on in this browser. It is a reading view, not secure access. Print the working sheet

Founding reader

Welcome back. · Issue 01

1 comment under this story on LinkedIn. Read the discussion

Keep reading

The ERP LEADERS brief Get issue 01