The Failure File

ERP programmes that stopped, overran or went to court.

The figure, the date and the source for each one. An entry needs a public figure or a court filing. Where the approved budget was published, we give it beside the final one. 3 entries since 8 September 2026, added as they are reported.

FigureProgramme, as reported
2 points

Grocery Outlet's SAP launch cut gross margin by almost 2 points.

Law360 reported that Judge Jon S. Tigar of the Northern District of California dismissed the proposed investor class action on 16 September.

Law360 · 17 Sept 2026 · SAP: 18 stories

£1.22bn

Asda's tech divorce from Walmart, including a new SAP system, cost £1.22bn.

Project Future separated the UK's third largest supermarket from Walmart's systems after the 2021 sale.

The Register · 9 Sept 2026 · Walmart: 2 stories

€200m

Zeiss stopped a €200m SAP build after six years.

Bloomberg reported on 7 September that the Oberkochen optics group, a key supplier to the chip industry, has overhauled its move to SAP's cloud after costs passed €200 million.

Bloomberg · 8 Sept 2026 · ZEISS: 2 stories

Method

What gets an entry
A programme that a named outlet or a court filing reports as stopped, overrun or in dispute, with a public figure. Each entry is decided case by case.
What the figure is
The number as the source gave it. The figures here are of different kinds (a programme cost, a separation cost, a margin effect) and are not comparable. A programme cost covers the whole programme, not one vendor's software.

Know of one we have missed, with a public source? Send it.

The ERP LEADERS brief

Get issue 01: the Zeiss case, for a steering committee

Each issue takes one programme and lays out what was reported, what the reports cannot tell you, and what a steering committee can ask each quarter. Issue 01 is on the site. Read issue 01

New issues appear on the site first, at /brief/. We never sell your address. Privacy