SAP's cloud go-live at Cologne's university hospital cannot move, its tender says. If the pharmacy is late, the hospital faces daily penalties.
TED, the EU's public tenders website, published the notice from Universitätsklinikum Köln on 16 November.
The hospital is buying help to make its pharmacy and its SAP-linked processes ready for S/4HANA, including links to SAP finance, purchasing and sales.
The date is fixed by technical milestones and contract deadlines with SAP and the firm installing the system, the hospital says, which is why it shortened the procedure. The system is RISE with SAP, SAP's cloud subscription. Hospital logistics and the pharmacy must both be working at go-live.
A delay, the notice says, would break ordering for life-saving medicines and chemotherapy drugs and put patient care at acute risk. On top of the daily penalties would come standby fees for the installer and the cost of running two systems side by side.
The three highest-scoring applicants will be invited to make offers, and the contract runs through 2027. The notice gives neither the go-live date nor the size of the penalties.
The deadline sits in the hospital's own SAP contracts. The pharmacy work is still being bought.
Sources
Our file on SAP
- 19 Nov
Microsoft's finance saves over 250,000 hours yearly with AI, it reports. It runs on SAP, though Microsoft sells ERP.
- 19 Nov
SAP customer Bestseller thought it had around 12,000 staff, it says. Its systems counted differently; the total was closer to 20,000.
- 19 Nov
SAP's AI for on-premises customers needs a cloud commitment, a user group chief says. Single-system firms must move all maintenance, he says.
- 18 Nov
Croatia's treasury wants SAP licence maintenance estimated at €410,540, a tender shows. Every bidder needs SAP's confirmation that it is authorised.
- 18 Nov
A Swiss hospital awarded SAP HR app work worth about CHF 64,000, a notice shows. Some HR work gets little digital help.
For your next steering committee
- 1Ask which design decisions in your programme would be expensive to reverse, and when each was last reviewed.
- 2Ask which expected benefits change if the implementation approach changes.
- 3Ask who owns a decision to change course, and where it would be recorded.
Issue 01 of the ERP LEADERS brief puts a timeline, the three-number review and six questions on one page. Read issue 01
Welcome back. · Issue 01