Skip to content

The news behind the software that runs companies, explained for everyone.

ERP programmes

Oracle settled UCLA's ERP dispute with $3.1m in credits. UCLA spent at least $213m.

UCLA has settled its dispute with Oracle over Oracle's cloud software for finance and administration (ERP, short for enterprise resource planning), the heart of its Ascend programme, The Register reported on 12 October.

ERP LEADERS news desk · · First reported by The Register · Edition no. 36
Photo: Beyond My Ken/Wikimedia, CC BY-SA 4.0 · original

Oracle waives $1.31 million in outstanding fees and grants $3.1 million in credits against future charges, valid until the end of May 2028. UCLA pays $350,000 of $1.66 million in disputed invoices.

Ascend started in April 2018 and was due to finish in July 2020. Its budget was $120 million, later revised to $98.9 million. The Daily Bruin reported at least $213 million spent. That figure covers the whole programme, not Oracle's bill. UCLA paused the switch-on of the new finance system in August 2024 and gave notice to terminate in June 2025.

UCLA said the software "lacked sufficient functionality to meet the University's requirements." Neither side admitted liability. Oracle did not respond to The Register.

The credits and the waiver add up to $4.41 million, about 2% of the $213 million. The credits count only against Oracle charges UCLA still pays before May 2028.

If your ERP programme stopped after six years, would credits from the same vendor settle it for you?

Sources

Spotted an error? Tell us. Every correction is logged on Standards.

Your reading room

Companies in this story

Our file on Oracle

  1. 11 Oct

    Oracle spent $28.5 billion in one quarter. Its long-term debt passed $160 billion.

  2. 8 Oct

    SAP said old ERP on Oracle loses its patches after 2030. Even SAP-sold licences.

  3. 6 Oct

    FBI removed an Accenture contractor over a missed patch. Oracle issued it in June.

  4. 5 Oct

    Oracle pledged $10 million to Nashville's orchestra. Its budget gap was $10 million.

  5. 3 Oct

    Oracle planned a Wisconsin AI campus for 2027. Its power hook-up is still unapproved.

All 23 Oracle stories

Every story here is open to read. The ERP LEADERS brief goes one step further.

The day in enterprise software, in one email: the stories that matter, the failures with their figures, one case taken apart. Read a sample or sign up for the brief.

Founding reader

Welcome back. · Issue 01

Keep reading

The ERP LEADERS brief Subscribe